Tünel kal›p sistemleri / Tunnel formwork systems

Tünel kal›p uygulamas› günlük ifl program›
Tunnel formwork application daily working programme

Saat 8 9 10 11 12 13 14 15 16 17

Kal›p söküm haz›rl›¤›
Preperation of dismountling formwork

Kal›plar›n sökülmesi, tafl›nmas› ve perde demirlerinin ba¤lanmas›
Removing of the formwork and connecting wall reinforcement
Rezervasyon ve al›n elemanlar›n›n ba¤lanmas›
Connecting the opening form and stopends

Tabliye demirleri ve elektrik borular›n›n montaj›
Slab reinforcement works and connecting of electricity circuit

Beton dökümü ve kür ifllemleri
Concreting and by heat fast setting

Vinç çal›flmalar› / Crane working rates

Kal›p rotasyonu
Formwork remaning

Demir iflleri
Reinforcement works

Beton iflleri
Concreting works

Bofl dilimler
Empty times

02

Günlük kal›p devir periyodu ile With 1/2 tunnel formwork system programmed
programlanan 1/2 tünel kal›p sistemi by daily formwork cycle period. Every day
uygulamas› ile 1/2 tabliyelik bir set kal›pla construction of two houses are completed
her gün iki konutun kaba inflaat›n› with a set of formwork and the program is
tamamlayarak iki günde bir kat infla realized by construction of one floor having
edilerek program gerçeklefltirilir. four flat for every two days.

Teknik-El Kal›p Sistemleri Teknik-El Kal›p Sistemleri

136 137

1/2 tabliye tünel kal›p plan›
1/2 tunnel formwork plan