Tünel kal›p sistemleri / Tunnel formwork systems
Tünel kal›p uygulamas› günlük ifl program›
Tunnel formwork application daily working programme
Saat 8 9 10 11 12 13 14 15 16 17
Kal›p söküm haz›rl›¤›
Preperation of dismountling formwork
Kal›plar›n sökülmesi, tafl›nmas› ve perde demirlerinin ba¤lanmas›
Removing of the formwork and connecting wall reinforcement
Rezervasyon ve al›n elemanlar›n›n ba¤lanmas›
Connecting the opening form and stopends
Tabliye demirleri ve elektrik borular›n›n montaj›
Slab reinforcement works and connecting of electricity circuit
Beton dökümü ve kür ifllemleri
Concreting and by heat fast setting
Vinç çal›flmalar› / Crane working rates
Kal›p rotasyonu
Formwork remaning
Demir iflleri
Reinforcement works
Beton iflleri
Concreting works
Bofl dilimler
Empty times
02
Günlük kal›p devir periyodu ile With 1/2 tunnel formwork system programmed
programlanan 1/2 tünel kal›p sistemi by daily formwork cycle period. Every day
uygulamas› ile 1/2 tabliyelik bir set kal›pla construction of two houses are completed
her gün iki konutun kaba inflaat›n› with a set of formwork and the program is
tamamlayarak iki günde bir kat infla realized by construction of one floor having
edilerek program gerçeklefltirilir. four flat for every two days.
Teknik-El Kal›p Sistemleri Teknik-El Kal›p Sistemleri
136 137
1/2 tabliye tünel kal›p plan›
1/2 tunnel formwork plan
Tünel kal›p uygulamas› günlük ifl program›
Tunnel formwork application daily working programme
Saat 8 9 10 11 12 13 14 15 16 17
Kal›p söküm haz›rl›¤›
Preperation of dismountling formwork
Kal›plar›n sökülmesi, tafl›nmas› ve perde demirlerinin ba¤lanmas›
Removing of the formwork and connecting wall reinforcement
Rezervasyon ve al›n elemanlar›n›n ba¤lanmas›
Connecting the opening form and stopends
Tabliye demirleri ve elektrik borular›n›n montaj›
Slab reinforcement works and connecting of electricity circuit
Beton dökümü ve kür ifllemleri
Concreting and by heat fast setting
Vinç çal›flmalar› / Crane working rates
Kal›p rotasyonu
Formwork remaning
Demir iflleri
Reinforcement works
Beton iflleri
Concreting works
Bofl dilimler
Empty times
02
Günlük kal›p devir periyodu ile With 1/2 tunnel formwork system programmed
programlanan 1/2 tünel kal›p sistemi by daily formwork cycle period. Every day
uygulamas› ile 1/2 tabliyelik bir set kal›pla construction of two houses are completed
her gün iki konutun kaba inflaat›n› with a set of formwork and the program is
tamamlayarak iki günde bir kat infla realized by construction of one floor having
edilerek program gerçeklefltirilir. four flat for every two days.
Teknik-El Kal›p Sistemleri Teknik-El Kal›p Sistemleri
136 137
1/2 tabliye tünel kal›p plan›
1/2 tunnel formwork plan